Oracle's 1.3 GW Wisconsin AI campus faces severe power delays as grid review restarts

Techradar

Oracle's Wisconsin campus may have finished buildings long before electricity arrived Regulators withdrew their completeness finding after ATC filed 564 additional documents Ten months of review ended without a decision and restarted from zero Oracle’s massive 1.3 GW AI data center campus in…